The task was completed for Zakład Robót Komunikacyjnych - DOM w Poznaniu as part of the task entitled: “Design and execution of construction works for the alteration of the track system at the Szczecin Gumieńce station in the Gm1 control area as part of the project entitled: “Works on the no. 408 and 409 railway lines Szczecin Główny – State border (Tantow)”.
Delivery, unloading and pre-installation of turnouts in blocks using the Switcher technology with a value of more than PLN 6 million (gross) carried out between 28 August and 19 November 2018.
As part of the implementation, we delivered two complete Rz 60E1-1200-1:18.5 Rz V≤160 km/h turnouts on pre-stressed concrete switch sleepers and seven Rz 60E1-500-1:12 sb V<120km/h structures on pre-stressed concrete switch sleepers.