KZN Rail Sp. z o.o.desktop 2 KZN Rail Sp. z o.o.mobile 2

Gdańsk

Delivery and installation of two tram turnouts with manual control mechanisms together with delivery and replacement of tracks at the Tram Depot Gdańsk-Nowy Port 

Delivery and installation of two tram turnouts with manual control mechanisms together with delivery and replacement of tracks at the Tram Depot Gdańsk-Nowy Port 

Gdańsk

For the Gdańskie Autobusy i Tramwaje we carried out the investment task entitled: “Delivery and installation of two tram turnouts with manual control mechanisms together with delivery and replacement of tracks at the Tram Depot Gdańsk-Nowy Port”. 

The works were carried out from 15 April 2024 to 17 May 2024. 

The scope of the task included: 

  • demolition of steel permanent way and paving stone within the area of replaced turnouts, inserts; 

  • earthworks; 

  • construction of ballast substructure at a depth of 15 cm under the sleeper/switch sleeper; 

  • delivery and replacement of about 35 meters of single track on pre-stressed concrete sleepers; 

  • delivery and installation of two turnouts on pre-stressed concrete switch sleepers, along with ballasting, tamping, profiling and connecting to the existing switch heating systems and the existing drainage network; 

  • delivery and installation of two manual control mechanisms; 

  • installation of fish plate joints using the thermite welding method; 

  • alteration of the stone pavement within the replaced turnouts and insets. 

 

Place

of investment

Show all realizations

Quality Policy:

From the very moment the company was founded, quality has been our focus. This approach guarantees due performance of construction projects, transparent and rational

conduct of business processes, and safety for our employees and associates. Read more

Quality Policy:

Strona korzysta z plików cookies w celu realizacji usług zgodnie z Polityką Cookies . Wszelkie warunki przychowywania oraz dostępu do plików cookie ustawiane są z poziomu Twojej przeglądarki.