We carried out an investment task in the “design and build” formula entitled: “Modernization of the Katowice – Rondo junction” for Tramwaje Śląskie S.A.
The total value of the investment task amounted to nearly PLN 7.7 million (gross) and the entire project was carried out in two stages: stage I between 25 June and 16 November 2018; and stage II between 14 June and 30 August 2019.
The scope of the task included:
- Preparation of design documentation and obtaining administrative decisions enabling the implementation of construction works.
- Modernization of the tram track with a total length of 660.6 meters of single track, including: demolition of the old permanent way, construction of a classic base of ballast on sleepers along with the construction of the ballast substructure and track tamping, installation of three road-tramway crossings using prefabricated track slabs
- Delivery and installation of three complete double-track single turnouts on wooden switch sleepers, together with the construction of a ballast layer and turnout tamping, along with point machines, as well as heating and drainage systems.
- Installation of expansion joints and rail lubrication devices with lubrication points.
- Tram track drainage.
- Topsoiling and grass sowing.




