Between 15 March 2021 and 30 November 2021, we carried out works under the task “Modernization of the tram track and catenary on the route of no. 2 line in the section from Niepodległości Square to Reja Street” in Toruń.
The task was divided into two stages:
-
Stage I – the section along Kraszewskiego Street
-
Stage II – the section along Broniewskiego Street, including the intersection of Reja and Broniewskiego Streets
A total of more than 2,575 meters of single track was modernized.
The scope of works included:
-
installation of tracks and turnouts on continuous grout
-
installation of tracks in prefabricated slabs (embedded rail system)
-
installation of expansion joints on pre-stressed concrete sleepers
-
construction of linear and point drainage of the track system
Place
of investment
Quality Policy:
From the very moment the company was founded, quality has been our focus. This approach guarantees due performance of construction projects, transparent and rational
conduct of business processes, and safety for our employees and associates. Read more