In accordance with the contract signed with Lubelski Węgiel “BOGDANKA” S.A., from 20 July 2021 to 2 August 2021 KZN Rail performed works related to the replacement of two turnouts at the Bogdanka mine railway siding. 

 

The works included:  

  • demolition of the existing permanent way,  

  • earthworks;  

  • construction of a subballast of 0–31.5 mm aggregate  

  • construction of a ballast sublayer,  

  • installation of Rz 49E1-190-1:9 turnouts,  

  • mechanical tamping with profiling.  

 

 

The total value of the works amounted to PLN 490, 770 .00 gross.   

Place

of investment

Show all realizations

Quality Policy:

From the very moment the company was founded, quality has been our focus. This approach guarantees due performance of construction projects, transparent and rational

conduct of business processes, and safety for our employees and associates. Read more

Quality Policy:

Strona korzysta z plików cookies w celu realizacji usług zgodnie z Polityką Cookies . Wszelkie warunki przychowywania oraz dostępu do plików cookie ustawiane są z poziomu Twojej przeglądarki.