As part of the project “Kombinat Turnout Junction from the Ujastek Mogilski Street side – Stage II”, KZN Rail Sp. z o.o. carried out trackwork for ZUE S.A.
The works were performed from 1 June 2026 to 7 June 2026 and included:
- Installation and alignment of large-format prefabricated turnout slabs, including the execution of a self-compacting levelling layer using flowable grouting technology – 11 units, 192 m²
- Installation of a single complete double-track turnout using ballastless technology in large-format prefabricated turnout slabs, including the execution of the rail-side zone and filling the joints between the slabs – 1 set