We carried out works related to the construction of the Kraków Zabłocie – Kraków Krzemionki junction railway in two stages for Budimex. As part of the works performed, the Switcher system was used commercially used for the first time for replacing the 60E1-500-1:12 turnout on a short shutdown.
The works were carried out in between 2015 and 2017, and their value exceeded PLN 5 million (gross)
The works included:
-
delivery and installation of turnouts (including one in block technology);
-
replacement of rails, sleepers, adding ballast;
-
delivery and installation of guard rails;
-
installation of expansion joints;
-
making welds and preserving joints;
-
track tamping and profiling.