Works carried out under the task “Alteration of the track system of the Radom Wschodni station through the installation of new turnouts and the alteration of railway equipment”
Delivery and unloading of turnouts in blocks using SWITCHER technology, PWP gantry system
Railway turnouts:
- R7600 - 4 sets
- R500 - 5 sets
We delivered all nine sets to Radom Wschodni station in three transports
Delivery date: November 2020–July 2021