Alteration of the Gliwice Port station with adjusting the tracks to the length of trains of at least 800 m as part of the program entitled: “Improving safety and eliminating operational hazards on the railway network” The task was performed by a consortium of SILTOR (leader) and KZN Rail.
The works with a value of almost PLN 40 million (gross) were completed between 13 July 2017 and 30 November 2018.
Discover our
partners’
opinions on our delivery
The object of the contract included:
- Preparation of detailed documentation for all industries (including modernization of more than seven kilometers of track, installation of a dozen turnouts, diamond crossings and buffer stops, drainage and dewatering; installation of point machines, signal lights and wheel sensors; up to wheel sensor – 42 pcs; installation and commissioning of the station Modest Gemini control command and signaling system and SUZ power supply; modernization of the catenary; installation of a new turnout heating system and LED lighting on poles of Gliwice Port station; renovation of the executive control station building);
- Execution of construction works in the design and build formula;
- Preparation of the as-built documentation, the surveying and cartographic documentation, terminal inspection report;
- Execution of the certification process for design documentation, equipment and structures intended for railway traffic management, as well as interoperability and subsystem components.
Place
of investment
Quality Policy:
From the very moment the company was founded, quality has been our focus. This approach guarantees due performance of construction projects, transparent and rational
conduct of business processes, and safety for our employees and associates. Read more