Deliveries of turnouts are underway as part of the “LOT A – Works on the 131 railway line in the Chorzów Batory (km 5.900) – Nakło Śląskie (km 29.000) section” task.
Delivery and unloading of turnouts in blocks using SWITCHER technology, PWP gantry system and crane covers the following stations: Bytom, Bytom Karb, Bytom Północ, Chorzów Batory, Chorzów Miasto, Chorzów Stary, Radzionków.
As part of the implementation, we will deliver a total of 130 sets, including:
- R1200 - 4 sets
- R760 - 3 sets
- R500 - 63 sets
- R300 - 56 sets
- R190 - 1 set
- RPDP SD - 8 sets