Modernization of the Przemyśl Bakończyce railway siding – one year has passed

A Year Has Passed Since the Start of the Przemyśl Bakończyce Railway Siding Redevelopment – and a Lot is Happening!

Twelve months ago, together with our Consortium Partner, Wadoma, we launched a modernization project that will transform the future operations of this site for years to come.

Today, intensive construction work is underway across many areas of the project:

  • We are continuing brickwork and sandwich panel installation in the workshop hall,

  • Structural works are ongoing on the office and administration building,

  • Masonry and reinforced concrete works have been completed in the rectifier building,

  • The walls of the new railway signal box are rising rapidly,

  • We are dismantling and rebuilding the culvert under the track system,

  • Our team is fully engaged in road construction works,

  • Work continues on the traction network and the installation of cabling infrastructure across the site,

  • Sanitary works are also being carried out with determination.

Last Saturday, we tackled yet another challenge — we delivered a turnout in blocks using the innovative "Switcher" system!
“Thanks to precise coordination and reliable technology, everything went according to plan. We thank everyone involved — we’re taking another step toward a more efficient rail infrastructure!”
— said Krzysztof Wróbel, Track Works Manager.

This project is where history meets innovation — with new tracks, modern installations, and infrastructure that will serve future generations.

We’re building the future of rail – every single day!

See other news

We have started the construction of a warehouse at the Przemyśl Bakończyce railway siding
07 listopada 2025
We have started the construction of a warehouse at the Przemyśl Bakończyce railway siding

Work on the Railway Infrastructure Construction Site in Przemyśl – Bakończyce is progressing according to schedule, an...

Reconstruction of Miechów Station
23 października 2025
Reconstruction of Miechów Station

In September 2025, we completed another stage of works as part of the reconstruction of railway stations along line no. 8, c...

KZN Rail at TRAKO 2025 – together with the KZN Bieżanów Group
12 września 2025
KZN Rail at TRAKO 2025 – together with the KZN Bieżanów Group

The TRAKO Trade Fair in Gdańsk is one of the most important railway industry events in Europe, and a place we have been part...

Dofinansowane przez UE
11 sierpnia 2025
Dofinansowane przez UE

European Funds for the project entitled: “Increasing the innovativeness of KZN Rail sp. z o.o. through the implementat...

We are completing the first stage of track works at Zawiszy Square in Warsaw
18 lipca 2025
We are completing the first stage of track works at Zawiszy Square in Warsaw

We are completing the first stage of track works at Zawiszy Square in Warsaw! We’ve finished applying the pourable...

Przemyśl Bakończyce
24 stycznia 2025
Przemyśl Bakończyce

The consortium of KZN Rail Sp. z o.o. and Wadoma W. Małkowiak, W. Bodziony spółka komandytowa is carrying out the pro...

We have started the construction of a warehouse at the Przemyśl Bakończyce railway siding
07 listopada 2025
We have started the construction of a warehouse at the Przemyśl Bakończyce railway siding

Work on the Railway Infrastructure Construction Site in Przemyśl – Bakończyce is progressing according to schedule, an...

Reconstruction of Miechów Station
23 października 2025
Reconstruction of Miechów Station

In September 2025, we completed another stage of works as part of the reconstruction of railway stations along line no. 8, c...

KZN Rail at TRAKO 2025 – together with the KZN Bieżanów Group
12 września 2025
KZN Rail at TRAKO 2025 – together with the KZN Bieżanów Group

The TRAKO Trade Fair in Gdańsk is one of the most important railway industry events in Europe, and a place we have been part...

Dofinansowane przez UE
11 sierpnia 2025
Dofinansowane przez UE

European Funds for the project entitled: “Increasing the innovativeness of KZN Rail sp. z o.o. through the implementat...

We are completing the first stage of track works at Zawiszy Square in Warsaw
18 lipca 2025
We are completing the first stage of track works at Zawiszy Square in Warsaw

We are completing the first stage of track works at Zawiszy Square in Warsaw! We’ve finished applying the pourable...

Przemyśl Bakończyce
24 stycznia 2025
Przemyśl Bakończyce

The consortium of KZN Rail Sp. z o.o. and Wadoma W. Małkowiak, W. Bodziony spółka komandytowa is carrying out the pro...

Strona korzysta z plików cookies w celu realizacji usług zgodnie z Polityką Cookies . Wszelkie warunki przychowywania oraz dostępu do plików cookie ustawiane są z poziomu Twojej przeglądarki.