Work on the Railway Infrastructure Construction Site in Przemyśl – Bakończyce is progressing according to schedule, and the various facilities are gradually taking their final shape.
Latest news from the site – we have started building the warehouse!
This is another key element of the project’s technical facilities, which will eventually be equipped with an overhead crane to facilitate handling and storage of components.
Other facilities are also advancing dynamically:
-
In the workshop and washing hall, flooring and technological channels are being completed. Tile installation in the washing area is scheduled to begin in mid-November.
-
The administration building has reached its full structural volume – finishing works are underway, including plastering, roof insulation, and roofing.
-
In the signal box, installation and plastering works are in progress.
-
Track works are progressing intensively – the tamping machine is operating at full capacity, ensuring perfect track geometry.
We have also completed the reconstruction of the access road from Batorego Street – an important element of the transport system that will improve access to the complex. At the same time, road works are in full swing, including earthworks, sub-base preparation, and surfacing and trackbed works.
See other news
23 października 2025
Reconstruction of Miechów Station
In September 2025, we completed another stage of works as part of the reconstruction of railway stations along line no. 8, c...

12 września 2025
KZN Rail at TRAKO 2025 – together with the KZN Bieżanów Group
The TRAKO Trade Fair in Gdańsk is one of the most important railway industry events in Europe, and a place we have been part...

11 sierpnia 2025
Dofinansowane przez UE
European Funds for the project entitled: “Increasing the innovativeness of KZN Rail sp. z o.o. through the implementat...
18 lipca 2025
We are completing the first stage of track works at Zawiszy Square in Warsaw
We are completing the first stage of track works at Zawiszy Square in Warsaw! We’ve finished applying the pourable...
07 lipca 2025
Modernization of the Przemyśl Bakończyce railway siding – one year has passed
A Year Has Passed Since the Start of the Przemyśl Bakończyce Railway Siding Redevelopment – and a Lot is Happening!...
24 stycznia 2025
Przemyśl Bakończyce
The consortium of KZN Rail Sp. z o.o. and Wadoma W. Małkowiak, W. Bodziony spółka komandytowa is carrying out the pro...